Acres of experience


Real Estate Investment in the U.S.

Land Entitlement: Steps, Deadlines, and Who Makes the Decisions in the United States

By , co-founder and CIO of LandQuireUpdated on 14-minute read

Table of Contents
  1. What is land entitlement?
  2. What are the steps involved in a land entitlement process?
  3. Zoning and Rezoning: How Does the Application Process Work?
  4. Preliminary and Final Drafts: What Is the Approval Timeline?
  5. Utilities, roads, environment: What other permits are required?
  6. How long does it take to obtain a land entitlement, and how much does it cost?
  7. What are the risks associated with a land entitlement?
  8. Who does what in a land entitlement process?
  9. How does LandQuire handle the entitlement process for its land?
  10. Frequently Asked Questions
Land entitlement: aerial view of a demarcated, undeveloped lot along a road, prior to obtaining planning permits

Land entitlement refers to the set of government permits that determine what can be built on a piece of land in the United States, and in what quantities.

It involves zoning, sometimes a change in zoning (rezoning), followed by a preliminary and final subdivision plan, and access to utility networks.

In Texas, the Local Government Code requires the city or county to make a decision on a comprehensive subdivision plan within 30 days.

The total duration depends on the land, the studies, and the public hearings. Here are the steps, the legal deadlines, the expected costs, the risks, and who makes the decisions at each stage.

In a nutshell

  • In Texas, a “plan” refers to the preliminary plan, the final plan, or the amended plan for a subdivision (Texas Local Government Code, § 212.001).
  • The city must approve, approve with conditions, or reject a subdivision plan within 30 days of its submission; if it is not rejected within that time, it is deemed approved (Art. 212.009).
  • After the applicant responds to the conditions set forth, the city has 15 days to make a decision (Art. 212.0095, as amended by HB 3699 of 2023).
  • A zoning change requires a public hearing; property owners located within 200 feet (approximately 60 m) must be notified in writing at least 10 days in advance (Sec. 211.007).
  • Filling in a wetland to develop land requires a federal “Section 404” permit, which is administered on a day-to-day basis by the U.S. Army Corps of Engineers (EPA, 2026).
  • LandQuire has sold 37 projects (5 full-cycle portfolios and 32 land resales), as of November 19, 2026; it manages the permitting process from start to finish.

What is land entitlement?

Land entitlement (also known as land rights) refers to the building rights that a parcel of land is granted by local authorities: permitted use, density, subdivision into lots, and connection to utility networks.

"Entitled" land is land for which these permits have been obtained: a builder knows what they can build on it.

An undeveloped lot, on the other hand, is often a plot of agricultural or forested land without an approved development plan.

In between, there is an administrative and technical process that can take several months or even several years.

Land entitlement does not include construction.

It ends when the land can be sold to a developer along with its permits, before road and utility work begins.

It also differs from land banking, which involves buying land and waiting for it to appreciate in value without applying for a permit.

In the United States, zoning regulations are set at the local level.

They vary from state to state and often from city to city: this article uses Texas as an example, where LandQuire is carrying out several of its projects.

What are the steps involved in a land entitlement process?

A land entitlement process generally involves six steps. Some of these steps occur simultaneously, and not all of them are necessary for every parcel of land.

StepWhat you getWho decides?
1. Site AnalysisCurrent Zoning, Constraints, FeasibilityThe project leader, along with a surveyor and an engineer
2. Zoning change (if necessary)A use and density tailored to the projectZoning Commission, followed by City Council
3. Preliminary Plan (preliminary plat)The division into lots and the street layout have been approvedCity Planning Commission, or county planning commission outside city limits
4. Technical StudiesCompliant roadways, drainage, water, and sewer systemsTechnical Services, Environmental Agencies
5. Final plan (final layout)The final plan, filed with the countyMember of the Planning Commission, then County Clerk
6. NetworksThe right to connect to water, electricity, and sewer servicesNetwork providers, based on a certificate of plan approval
Flowchart of the permitting process for a land entitlement in Texas: zoning, preliminary plan, final plan, utilities, and environmental permits, including the decision-making authority and the statutory timeframe for each step

1. Inspect the property before buying it

It all starts with an inspection of the property: title deed, boundary markers, access, easements, flood zones, wetlands, and current zoning regulations.

This step determines whether the project is feasible and at what cost. Our real estate due diligence checklist details the points to be reviewed.

2. Request a zoning change, if necessary

If the current zoning does not allow for the project (for example, land zoned for agricultural use but intended for a residential development), you must request a rezoning from the city.

This is the longest and most uncertain stage, as it involves public hearings and a vote by elected officials.

3. Have the preliminary plan approved

The preliminary plan shows the division into lots, the streets, and the areas set aside for public use.

In Texas, any property owner who subdivides a parcel of land or lays out streets within a city or its extraterritorial jurisdiction (ETJ) must have a subdivision plan prepared.

A subdivision of lots larger than 5 acres, all of which are serviced and have no public infrastructure to be transferred, does not require one.

The role of a city's catchment area is explained in our article onthe ETJ in Texas.

4. Conduct technical studies

City departments inspect roads, drainage systems, water supply, and sewer systems.

Depending on the site, additional permits may be required, such as an environmental permit for wetlands, a traffic study, and a groundwater study.

5. Have the final plan approved and registered

The final plan is based on the revised preliminary plan. Once approved, it is filed with the county clerk, at which point the parcels come into legal existence.

Details on this procedure can be found in our guide to the land approval process, and our article on subdividing a parcel of land explains the subdivision process itself.

6. Gain access to networks

In Texas, a city, county, or company that provides water, sewer, electricity, or gas services may not connect a parcel of land without a certificate of approval for its subdivision plan.

Zoning and Rezoning: How Does the Application Process Work?

Zoning divides a city into zones where land use, density, building height, and building footprint are regulated.

In Texas, these rules must comply with the city’s comprehensive plan, according toSection 211.004 of the Texas Local Government Code.

A rezoning request follows a process governed by the Texas Code:

  1. The zoning commission drafts a preliminary report and holds at least one public hearing.
  2. Neighbors who own property within 200 feet are notified in writing at least 10 days before this hearing.
  3. The public is notified through an announcement published in a local newspaper and on the city’s website, if it has one, at least 15 days before the hearing of the elected officials.
  4. The city council will vote after receiving the commission's final report.

Neighbors may object.

If the owners of at least 20% of the affected or adjacent lots sign a written objection, the change must, in principle, be approved by a three-quarters majority of the council.

Effective September 1, 2025 (HB 24), the threshold is reduced to 60% of neighboring lots when the change is intended solely to increase the number of housing units, in which case a majority vote is sufficient.

Outside city limits in Texas, it is the county (commissioners court) that approves subdivision plans.

Preliminary and Final Drafts: What Is the Approval Timeline?

Texas sets a deadline for reviewing subdivision plans. According toSection 212.009 of the Texas Local Government Code, the city must make a decision within 30 days of filing.

It may approve, approve with conditions, or reject the plan. A plan that is not rejected within this time frame is approved.

Each condition or ground for refusal must be in writing, consistent with applicable rules, cite the relevant legal provision, and not be arbitrary.

The applicant may respond at any time: the city cannot impose a deadline. The city then has 15 days to rule on the applicant’s response.

The city must publish a written list of the documents to be included in the application; an application that contains all of them is considered complete.

The 30-day period may be extended, upon the applicant's written request, in periods of no more than 30 days.

Counties follow a similar rule: 30 days after receiving a complete application (Section 232.0025).

Example: The minimum statutory timeline for a preliminary plan in Texas

DayWhat's Going OnText
Day 0Submission of the complete application to the Planning CommissionSecs. 212.008 and 212.0081
No later than Day 30Decision: approval, conditional approval, or a reasoned denialSecs. 212.009 and 212.0091
Date selected by the applicantWritten response to the requirements, with corrected diagramsSec. 212.0093
15 days after the responseNew decision; approval if the response meets all conditionsSec. 212.0095

If the city council must also approve the plan, it, in turn, has 30 days after the committee’s approval.

The same process is repeated for the final plan. This timeline includes only the time spent reviewing the plans; the time required for preparing the plans, conducting studies, and making corrections is not included.

Utilities, roads, environment: What other permits are required?

A subdivision plan is approved only if it is consistent with the city’s plan for its streets, parks, and utility networks, including the extension of water and sewer lines.

The city may also establish standards for street construction and drainage for each housing development.

Permit documentation for a parcel of land: stamped subdivision plan, zoning map, and photos of the site’s waterways and wetlands

Environmental constraints often carry more weight.

According tothe Environmental Protection Agency (EPA), Section 404 regulates the filling of water bodies in the United States, including wetlands.

The fill material for the development is involved, and the U.S. Army Corps of Engineers is reviewing the permit applications.

Flood risk is shown on maps published by the federal agency FEMA: an area with at least a 1% chance of flooding each year is classified as high-risk.

A plot of land in a wetland or flood-prone area isn't necessarily out of the question, but it requires more studies, more time, and sometimes fewer lots.

How long does it take to obtain a land entitlement, and how much does it cost?

There is no standard duration. The Texas Code sets review deadlines, not the total duration of the project.

This depends primarily on four factors:

FactorImpact on the schedule
Zoning Already Suitable for the ProjectNo rezoning hearing: the case proceeds directly to the subdivision plan
Nearby Water and Sewer SystemsFewer studies and projects are needed to secure the connection
Wetlands or flood-prone areasAdditional studies and permits, including the federal Section 404 permit
Neighbors' OppositionA more contentious hearing, a possible strengthened vote, and the risk of postponement or rejection

Costs follow the same logic.

They include the fees for the surveyor and civil engineer, technical and environmental studies, filing fees set by each city, and, in some cases, a specialized attorney.

We do not provide a general range: it would not make sense from one county to another.

At LandQuire, these fees are included in the budget for each project, as detailed in the private placement memorandum (PPM) provided prior to subscription.

What are the risks associated with a land entitlement?

This process creates value because it involves risks that the manufacturer does not want to bear. The main ones are:

  • the rejection of the rezoning or the plan, or of conditions that reduce the number of lots;
  • delays: successive corrections, postponed hearings, additional studies;
  • opposition from neighbors, which may require a supermajority vote by elected officials;
  • site constraints discovered late: wetlands, flood zone, access, easement;
  • changes to local or state regulations during the course of the project;
  • The market: demand from manufacturers at the time of resale.

For investors, a delay ties up capital for a longer period and reduces the annual return.

A rejection may force the owner to resell the land without the required permits, with the risk of a financial loss.

Who does what in a land entitlement process?

ActorRole
Project Manager (at LandQuire, the project company)Purchase the land, finance and manage applications, and resell the approved land
SurveyorBoundary marking, field survey, description of the plan based on its boundaries
Civil EngineerSubdivision plans, road systems, drainage, utility networks
Zoning Commission and Planning CommissionPublic hearings, recommendations, approval of plans
City Council or County Commissioners CourtRezoning vote; approval of plans in accordance with local regulations
County ClerkFiling of the Final Plan
U.S. Army Corps of EngineersSection 404 Permit in a Wetland Area
Network ProvidersWater, Sewer, and Electricity Connections
NeighborsInformation, remarks made during the hearing, written objection

How does LandQuire handle the entitlement process for its land?

LandQuire is an American company founded in 2021 by Romain Daniellou and Thibaut Guéant.

It buys land on the outskirts of growing cities, obtains the necessary permits, and then resells it to developers.

The team analyzes all 3,143 U.S. counties using an algorithm with more than 120 criteria for selecting land parcels.

LandQuire manages each project from start to finish: sourcing, acquisition, permitting, resale, and the legal and financial management of the project company.

LandQuire has sold 37 projects (5 full-cycle portfolios and 32 land resales), as of November 19, 2026. In Wake Village, Bowie County, Texas, an 11.76-acre parcel zoned for 34 lots followed this process: purchase, subdivision plan, resale.

The other projects that have been sold are listed on our page for sold real estate projects.

Each parcel of land is owned by a project company, which is expected to operate for approximately 36 months, with no guarantee (plan for 5 years or more).

The minimum grant amount is $100,000 per project.

The fees are included in the project budget, with no annual management fees, and recent offerings are made to non-U.S. residents under Regulation S.

This step is central to the development of a piece of land.

Our guide toreal estate investing in the United States places it among the other ways to invest in U.S. real estate.

To view properties currently being developed that are open for investment, check out our real estate listings in the United States.

Frequently Asked Questions

What is land entitlement?

It is the granting of public permits—or building rights—that determines what can be built on a parcel of land: zoning, subdivision plans, and access to utility networks.

A "titled" lot can be sold to a builder who knows how many homes he can build on it.

What is the difference between zoning and rezoning?

Zoning refers to the regulations in effect for a piece of land: land use, density, and building height.

Rezoning is a request to change this rule—for example, to change the land use from agricultural to residential. It requires a public hearing and a vote by elected officials.

What are an appetizer and a main course?

The preliminary plan shows the proposed lot subdivision and the street layout.

The final plan incorporates these changes following corrections and reviews; once approved, it is filed with the county, and the lots become legally established.

How long does a land entitlement last?

There is no standard timeframe: it can range from a few months to several years, depending on the terrain.

In Texas, the code only sets review deadlines: 30 days for each subdivision plan filed, followed by 15 days to rule on the applicant’s response to the conditions imposed.

Can a city reject a subdivision plan?

Yes, but in Texas, it must provide a written justification for each denial, citing the relevant legal provision, without exercising arbitrary discretion.

It must approve a plan that complies with the applicable rules, and any plan not rejected within 30 days is deemed approved.

What are the risks associated with a land entitlement?

Rejections or conditions that reduce the number of lots, delays, opposition from neighbors, environmental constraints discovered too late, and market changes.

These risks may extend the duration of the investment or result in a loss.

Who issues the permits?

The rezoning is approved by the city council following a recommendation from the zoning commission.

Subdivision plans are approved by the planning commission, or by the county outside city limits.

Wetland permits are issued by the U.S. Army Corps of Engineers.

Can you invest in land entitlement from France?

Yes, by co-investing in a U.S. project company that purchases the land and manages the permitting process.

At LandQuire, the minimum investment is $100,000 per project, either in your own name or through an LLC, with a U.S. tax ID.

Are you looking for an investment backed by real estate, managed from purchase through resale?

Explore our land opportunities in the United States, learn about our land sourcing and entitlement process, or get in touch with the LandQuire team.

This article is for informational purposes only and does not constitute personalized legal, tax, or investment advice.

The rules cited are those in effect in Texas as of October 2026; they vary by state, city, and county.

Any real estate investment carries the risk of a loss of principal and ties up your money for several years.

About the Author

Thibaut Guéant

Thibaut Guéant, co-founder and CIO of LandQuire, founded the company in 2021 with Romain Daniellou. As a land entitlement specialist, he identifies off-market raw land, primarily in Texas, and oversees the process of obtaining zoning permits that make the land buildable before reselling it to developers.

View the author's pageLinkedInSchedule an appointment

Leave a comment

Your e-mail address will not be published. Required fields are marked with *.

Recommended Articles

Ready to invest in U.S. real estate?

Create your free account to access the projects, the pro forma, and the data room.